INTERIOR FINISHING OF APARTMENT
June 4, 2024AMSTERDAM, THE NETHERLANDS
Floor area: 192 sq.m.
Duration of the work: 5 months.
- The apartment reconstruction project has been implemented according to the client’s wishes.
- New walls built according to the new layout.
- A bathroom installed and fitted with a new piping system.
- Electrical installation renewed.
- Interior finishing: plastering, daubing and painting of the walls.
- Ceilings installed, maintaining the desired maximum ceiling height.
- Tiling of the sanitary units carried out..
- Interior doors installed and painted.
- A modern lighting system installed.
- Kitchen furniture fitted.